If 12 men can do a piece of work in 80 days in how many days will 16 men do it

Answer»

Answer:

60 days

Step-by-step EXPLANATION:

Men|12|16

Day |80|y1

x*y=x1*y1

12*80=16*y1

960/16=y1

60=y1