How many days will 1300 men take to dig trench, if 625 men can do the same in 52 days​

Answer»

For this one our output is 'trenches' and our inputs are men and days. EXPRESSING the example algebraically we have 6 trenches = 3 men times four days.

6t = 3m x 4d

To generalise the input for one TRENCH, we need to CREATE a hybid unit, the 'manday'. The number of mandays is the product of its inputs. So:

6t = 12 mandays

Solving for one trench gets us:

t = 2 md.

We can use this to solve the problem, how many days for 4 men to do 24 trenches.

24t = 48md.

We can find the number of days by dividing by our KNOWN number of men.

48 md / 4 men = 12 days.