Saved Bookmarks
| 1. |
For the construction of buildings, the subheads of the estimate are ________(a) Earthwork, Concrete work, Brick work(b) Plastering or pointing, finishing, water supply and sanitary work(c) Brickwork Flooring, Wood work, Steel work(d) Earthwork, concrete work, brick work, plastering, water supply and steel work |
|
Answer» Right answer is (d) Earthwork, concrete work, brick work, plastering, water supply and steel work Easy explanation: This method is suitable for walls of similar cross sections. Here the total centre line length is multiplied by breadth and depth of respective item to get the total quantity at a time. When cross walls or partitions or verandah walls join with main wall, the centre line length gets reduced by half of breadth for each junction. Such junction or joints are studied carefully while calculating total centre line length. The estimates prepared by this method are most accurate and quick. |
|