1.

For preparation of subgrade the existing subgrade should be dressed to a camber of 1 in 24 to 1 in 32.(a) True(b) FalseI got this question in an interview for internship.My query is from Types of Construction and Specification topic in division Village Housing of Civil Engineering Drawing

Answer»

The correct answer is (a) True

The best I can explain: It is watered and allowed to SOAK for the night if NECESSARY, and rolled with 8 to 10 tonne road roller. The density of the compacted SOIL should not be less than 1.8 GM /c.c. up to at least 6” depth.