Explain the difference between basic scheduling and lead time scheduling? |
|
Answer» Basic Scheduling It only calculates basic dates for orders in MRP run and in house production time for material master in use. Lead time Scheduling In this MRP, production dates are defined by lead time scheduling for planned orders. |
|