Azar can do a piece of work in 22 days. niya can do a same work in 16.5 days and saheer can do in 27.5 days. niya and saheer starts the work and leave after 7.5 dyas |
|
Answer» Here is the answer 6 DAYS will be taken by azar to complete REMAINING WORK |
|