1.

After a flood had passed an observation station on a river, an engineer visited the site. By locating flood marks, performing appropriate surveying and doing necessary computations determine that cross-sectional area, wetted perimeter and water surface slope at the time of peak flooding were 2860 m2, 320 m and 7.2 ×10−4 respectively. The channel bottom roughness coefficient is estimated to be 0.027. The peak flood discharge at the observation station is (in cumecs).12240.8

Answer» After a flood had passed an observation station on a river, an engineer visited the site. By locating flood marks, performing appropriate surveying and doing necessary computations determine that cross-sectional area, wetted perimeter and water surface slope at the time of peak flooding were 2860 m2, 320 m and 7.2 ×104 respectively. The channel bottom roughness coefficient is estimated to be 0.027. The peak flood discharge at the observation station is (in cumecs).
  1. 12240.8