a takes 9 days more than B to do a piece of work together can do a work in 6 days how many days will a alone take to do the work |
|
Answer» time taken by A=9+x A/Q =A+B=6day's =9+x+x=6 =×+×=6-9 =2x=3 =×=3/2 therefore, time taken by A=×+9 And,x=3/2 A=3/2+9 =21/2 |
|