A takes 10 days less than the time taken by B to finish a piece of work If both A and B together can finish the work in 12 days the time taken by B to finish the work is

Answer»

Let B alone finish the work = x days.

And Alone finish the work = (x−10) days

A' s one day work = 1/x-10

B' s one day work = 1/x

As it given the

(A + B)  can finish work in 12 days

∴ (A + B) one daywork = 1/21​

⇒ A′ some day work + B′ some day work = 1/12

⇒ \(\frac{1}{x-10}+\frac{1}{x}=\frac{1}{2}\)

⇒ \(\frac{x+x-10}{x(x-10)}=\frac{1}{12}\)

⇒ \(\frac{2x+x-10}{x(x-10)}=\frac{1}{12}\)

⇒ 12(2x−10) = x(x−10)

⇒ 24x − 120 = x2 − 10x

⇒ x− 10x − 24x + 120 = 0

⇒ x2 − 34x + 120 = 0

⇒ x− 30x − 4x + 120 = 0

⇒ x(x−30) − 4(x−30) = 0

⇒ (x−4)(x−30) = 0

⇒ x = 4 or x = 30

x = 4

∵ if x = 4 then A alone can finish the work in = (4−10) = −6 days which is not possible

∴ x = 30 days