A project has four activities P, Q, R and S as shown below. Activity Normal duration (days) Predecessor Cost slope (Rs./day) P 3 - 500 Q 7 P 100 R 4 P 400 S 5 R 200 The normal cost of the project is Rs. 10,000/- and the overhead cost is Rs. 200/- per day. If the project duration has to be crashed down to 9 days, the total cost (in Rupees) of the project is 12500

Answer» A project has four activities P, Q, R and S as shown below.



































Activity Normal duration (days) Predecessor Cost slope (Rs./day)
P 3 - 500
Q 7 P 100
R 4 P 400
S 5 R 200



The normal cost of the project is Rs. 10,000/- and the overhead cost is Rs. 200/- per day. If the project duration has to be crashed down to 9 days, the total cost (in Rupees) of the project is
  1. 12500