A project consists of six activities. The immediate predecessor of each activity and the estimated duration is also provided in the table below: Activity Immediate predecessor Estimated duration (weeks) P - 5 Q - 1 R Q 2 S P, R 4 T P 6 U S, T 3 If all the activities other than S take the estimated amount of time, the maximum duration (in weeks) of the activity S without delaying the completion of the project is 6 |
|||||||||||||||||||||
Answer» A project consists of six activities. The immediate predecessor of each activity and the estimated duration is also provided in the table below:
If all the activities other than S take the estimated amount of time, the maximum duration (in weeks) of the activity S without delaying the completion of the project is
|
||||||||||||||||||||||