A project as expected mean duration of 20 days of variance of three days what is the probability of finishing the project in 22 days? |
|
Answer» Answer: A PROJECT as EXPECTED mean DURATION of 20 days of variance of three days what is the probability of finishing the project in 22 days? |
|