A printer A can print 1 lakh books in 16 hours, printer B can print the same number of books in 20 hrs while printer C can print them in 24 hrs. All the printers are started at 5 p.m. while printer A is closed at 10 p.m. and the remaining two printers complete the work. Approximately at what time will the work be finished? |
|
Answer» A printer A can print 1 lakh books in 16 hours, printer B can print the same number of books in 20 hrs while printer C can print them in 24 hrs. All the printers are started at 5 p.m. while printer A is closed at 10 p.m. and the remaining two printers complete the work. Approximately at what time will the work be finished?
|
|