A particular work can be completed by 6 men and 6 women in 24 days; whereas the same work can be completed by 8 men and 12 women in 15 days. Find: i) According to the amount of work done, one man is equivalent to how many women. ii) The time taken by 4 men and 6 women to complete the same work. |
|
Answer» A particular work can be completed by 6 men and 6 women in 24 days; whereas the same work can be completed by 8 men and 12 women in 15 days. Find: i) According to the amount of work done, one man is equivalent to how many women. ii) The time taken by 4 men and 6 women to complete the same work. |
|