A manufacturing plant, working in 2 shifts of 8 hrs each, produces 30,000 switch boards using a set of 7 workstations in series. The cycle time, in seconds, is _______ |
|
Answer» Concept : Net Production Time = Cycle Time \(\times\) Number of Units Produced Calculation: Given: Net Production Time = \(2\times8 \times3600\) = 57600 sec Number of Units Produced = 30000 \(Cycle\; time = \frac{Net \;Production\; time}{Number\;of\;Units\;Produced}\) \(Cycle\; time = \frac{57600}{30000} =1.9\) ∴ Cycle time = 1.9 sec |
|