A man can finish a job in 44 days. 3 men can do the same work in a day as isdone by 5 women. 2 women can do the same work in a day as a done by 3boys. A contractor employs 5 men, 8 women and 3 boys to finish a work. Inhow many days would the work be finished ? |
|
Answer» Answer: 29 is your ans Step-by-step EXPLANATION: |
|