a does work in 6 days b in 8 days and c in 10 days. a worked alone for 2 days before leaving and then b and c worked together for 2 days and after that b left the remaining work was finished by c alone. how long did it take to finish the work

Answer» 2 1/13 is a CRCT ANSWER