A contract on construction of job spacifies a penalityfor delay of completion beyond a certain date asfollows? 200 for the first day, 250 for the 2ndday, 300 for the third day, etc. The penality foreach succeeding day being 50 more than thepreceeding day. How much money the coutractarhas to pay as penality, if he delayed the work by 90days.