A contract on construction job specifies a penalty for delay of completion beyond a a certain date as follows: ₹200 for the first day, ₹250 for the second day, ₹300 for the third day, etc., the penalty for each succeeding day being ₹50 more than for the preceding day. How much money the contractor has to pay as penalty, if he delayed the work by 30 days? |
| Answer» A contract on construction job specifies a penalty for delay of completion beyond a a certain date as follows: ₹200 for the first day, ₹250 for the second day, ₹300 for the third day, etc., the penalty for each succeeding day being ₹50 more than for the preceding day. How much money the contractor has to pay as penalty, if he delayed the work by 30 days? | |