A certain number of men can finish a price of work in 100 days .If there were 10 men less ,it would take them 10 days more to finish the work. How many men were there originally? |
| Answer» A certain number of men can finish a price of work in 100 days .If there were 10 men less ,it would take them 10 days more to finish the work. How many men were there originally? | |