1.

A can finish an it project in 15 days, b can finish the same project in 12 days. in how many days, both of them can finish 60% of the project? it may be assumed that working together does not impact their productivity.

Answer»

A can finish the PROJECT in 15 days.


B can finish the project in 12 days.


A and B can finish the project in

\cfrac{15 \times 12}{15 +12} = \cfrac{20}{3}  = 6\cfrac{2}{3}\text { days}


60% of the project can be COMPLETED in:

60\% \times 6\cfrac{2}{3}  = \cfrac{60}{100} \times \cfrac{20}{3}  = 4 \text { days}


ANSWER: 4 days