A can do a piece of work in 20 days while B alone can do In 12 days. B worked at it for 9 days. A can finish the remaining work in A. 3 days B. 5 days C. 7 days D. 11 days |
|
Answer» Number of days A required do a piece of work : 20 Number of days B required do a piece of work : 12 Work done by A in one day: \(\frac{1}{20}\) Work done by B in one day: \(\frac{1}{12}\) B works alone for 9 days, so work completed by B in 9 days : \(9\times\frac{1}{12}=\frac{3}{4}\) Work left = \(1-\frac{3}{4}=\frac{1}{4}\) But \(\frac{3}{4}\)th of the work is already done by B ∴ Time required to complete the remaining \(\frac{1}{4}\)th of the work by A : \(\frac{1}{4}\times20\) = 5 days ∴ Time taken to finish the work 9 + 5 = 14 days ∴ A can finish the remaining work in : 5 days |
|