A can do a piece of work in 15 days. B is50% more than efficient than A. In how many days B can finish it? please solve it step by step |
|
Answer» Answer: 30 Step-by-step explanation: 50 prcent of x=15 50/100×x=15 x=15×100/50 =30 |
|