1.

A and B separately can build a wall in 12 and 16 days, respectively. If they work for 1 day alternatively, starting with A, in how many days will the wall be built?1. \(7{2\ \over3}\) days2. \(13{2\ \over3}\) days3. \(12{2\ \over3}\) days4. \(6{2\ \over3}\) days

Answer» Correct Answer - Option 2 : \(13{2\ \over3}\) days

Given :

A can do a work in 12 days 

B can do the same work in 16 days 

They work on alternate days 

Concept used :

work done each day = total work/total number of days

Calculations :

Total work = LCM of 12 and 16 

⇒ 48 units 

A's per day work = 48/12 = 4 units 

B's per day work = 48/16 = 3 units 

Total work done in 13 days  (7 days of A and 6 days of B) = 7 × 4 + 6 × 3 = 46 units 

Remaining work = 48 – 46 = 2 units 

Time taken by B to complete the remaining work = 2/3  (B's turn to do the work)

⇒ 2/3 days

Total time taken = 13 + 2/3 

⇒ \(13{2\ \over3}\)  days

∴ Total \(13{2\ \over3}\) days will be taken to complete the work



Discussion

No Comment Found

Related InterviewSolutions