A and B can together complete a work in 10 days. A alone can do it in 18 days. How long would Balone take to complete the work? |
|
Answer» Step-by-step EXPLANATION: In 10 days A + B can so = 1 work In 1 DAY A+B can do = 1/10 work In 15 days A can do = 1 work In 1 day A can do = 1/15 work Let in x days B can do = 1 work so in 1DAY B can do 1/x work In 1 day A+B can do = 1/10 work 1/15 + 1/x = 1/10 1/x = 1/10 - 1/15 1/x = 1/30 x = 30 |
|