A and B can do a piece of work in 12 days, B and C in 15 days, C and A in 20 days. How much time will A alone take to finish the work​

Answer»

Answer:

30 DAYS.

Step-by-step explanation:

2(A+B+C) 1 DAY WORK=1 UPON 12 + 1 UPON 15 +1 UPON 20.

2(A+B+C)1 DAY WORK=12 UPON 60=1 UPON 5.

(A+B+C)1 DAY WORK=1 UPON 5INTO2=1 UPON 10.

A'S 1 DAY WORK=(A+B+C)1 DAY WORK-(B+C)1 DAY WORK.

A'S 1 DAY WORK=1 UPON 10-1 UPON 15.

A'S 1 DAY WORK=1 UPON 30.

NO. OF DAYS=1 UPON 1 DAY WORK.

NO. OF DAYS=1/1 UPON 30.

NO. OF DAYS=30 DAYS.

ANS=A ALONE WILL COMPLETE THE WORK IN 30 DAYS.

THANK YOU.