A alone can finish a piece of work in 8 days and B alone can do it in 12 days .How many time will be taken,if both A and B work together? |
|
Answer» Step-by-step EXPLANATION: Both A and B can complete 1/12th work in one day So A+B=1/12 in one day A alone can complete 1/20 th work A=1/20 in one day Now B alone how much work can complete (1/20)+B=1/12 B =(1/12)-(1/20) L.C.M of 12 and 20 is 60 So B=( (5–3)/60) B=2/60=1/30 So alone can complete 1/30th work in one day B alone can complete the work in 30 days |
|