1.

7 men can complete a piece of work in 12 days they started the work and after 5 days two men left in how many days will the work be completed by the same element

Answer»

Total units of work = 7 men * 12 days = 84 units of work

For 5 days, 7 men worked => 7*5 = 35 units of work COMPLETED

Remaining (84 - 35) = 49 units of work need to be completed by (7 - 2) = 5 men

So, No. of days REQUIRED for remaining work to complete = 49/5 = 9 (4/5) days = 9.8 days


Regards,

KKKoppu



Discussion

No Comment Found

Related InterviewSolutions