4. men or 6 women can finish a work in 16 days.In how many days the same work is completed by2 men and 9 women ?(1) 12 days(2) 10 days(3) 9 days(4) 8 days​

Answer»

Answer:

9

Step-by-step explanation:

4. MEN or 6 women can finish a work in 16 days.

In how many days the same work is COMPLETED by

2 men and 9 women ?

(1) 12 days

(2) 10 days

(3) 9 days

(4) 8 days