4 men and 10 women were put on a work. They completed 13 of the work in 4 days. After this, 2 men and 2 women were increased. They completed 29 more of the work in 2 days. If the remaining work is to be completed in 3 days, then how many more women must be increased? |
|
Answer» 4 men and 10 women were put on a work. They completed 13 of the work in 4 days. After this, 2 men and 2 women were increased. They completed 29 more of the work in 2 days. If the remaining work is to be completed in 3 days, then how many more women must be increased? |
|