39 persons can repair a road in a 12 days working 5 hours per day in how many days will 30 person working 6 hours per day complete the work​

Answer»

ong>Answer:

et the required number of days be x.

Less PERSONS, More days (Indirect PROPORTION)

More working hours PER day, Less days (Indirect Proportion)

Persons30:39Working hours/day6:5}⋮⋮ 12:x

 

=> 30 * 6 * x = 39 * 5 * 12  

 

=> x= 13