36 men can do a piece of work in 12 days. In how many days 9 men can do the same work?

Answer»

Number of workers and number of days are in inverse proportion 

∴ x1 y1 = x2 y let y2 = x (say)

= 36 × 12 = 9 × x 

x = (36 x 12)/9 = 48 

∴ x = 48 days