36 men can do a piece of work in 12 days. In how many days 9 men can do the same work? |
|
Answer» Number of workers and number of days are in inverse proportion ∴ x1 y1 = x2 y2 let y2 = x (say) = 36 × 12 = 9 × x x = (36 x 12)/9 = 48 ∴ x = 48 days |
|