30 persons can reap a field in 17 days. How many more persons should be engaged to reap the same field in 10 days? |
|
Answer» ∵30 persons can reap a field in 17 days. 1 person can reap the same field in 30×17 i.e. 510 days. In 10 days, the number of persons required = 510/10 = 51 persons. |
|