30 men can finish a piece of work in 28 days. How many days will be taken by 21 men to finish. |
|
Answer» More the no. of men, lesser the days. So, it is an inverse proportion. Let the required time be x days. ⇒ 30 × 28 = 21 × x ⇒ x = \(\frac{30\,\times\,28}{21}\) = 40 days |
|