1.

25 workers can complete a task in 150days. How many workers will berequired to complete the task in 125days?

Answer»

25 worker complete the work in 150 days 1 worker will complete in 150÷25 =5worker required to complete the work in 125 days = 125×5=750 so , 750 worker are required