24 men can complete a piece of work in 15 days. 2 days after the 24 men started working, 4 men left the work. How many more days will the remaining men now take to complete the remaining work? |
|
Answer» 24 men can complete a piece of work in 15 days. 2 days after the 24 men started working, 4 men left the work. How many more days will the remaining men now take to complete the remaining work? |
|