Saved Bookmarks
| 1. |
20 labourers, working 7 hours a day can finish a piece of work in 30 days. If the labourers work 5 hours a day, then the number of labourers required to finish the same piece of work in 40 days, will be?1. 212. 243. 184. 295. None of these |
|
Answer» Correct Answer - Option 1 : 21 Given: 20 labourers, working 7 hours a day can finish a piece of work in 30 days The next set of labourers work for 5 hours a day, finishes the work in 40 days. Concept used: M1 × D1 × H1 ÷ W1 = M2 × D2 × H2 ÷ W2 Where M → number of people, D → number of days, H → hours W → wages, work Calculation: Let the number of men working be x. Applying the formula here, 20 × 7 × 30 = x × 5 × 40 ⇒ x = (20 × 7 × 30)/(5 × 40) = 21 ∴ 21 labourers will work to finish the work. |
|