2 women and 3 children can do a piece of work in 10 days while 3 women and 2 children can dobthe same work in 8 days. In how many days can 2 women and 1 children do the work?​

Answer»

ANSWER:

It TAKES 4 2/5 DAYS for them to COMPLETE.