2.5SoIf 12 men can dig a pond in 8 days. How manymen can dig it in 6 days?​

Answer»

er:the answer is 4 DAYS

Step-by-step explanation:

12 MEN can DIG in = 8 days

So 6 men can dig in = 8/12 multiply 6= 4 days