2. 15 men do a work in 25 days. In how many days the 20 men will complete thesame work.(a) 18(b)18(c) 15(d) 164

Answer»

15 men can do a work in 25 daystotal men x work= 25*15= 375

now suppose they will complete in x daysso x*20= 375x= 18.75 days