1.

16m of fencing was laid by 4 workers in 6 hours. How many workersrequired to lay 108 m of fencing in the same time? 2.7

Answer»

16 m of fencing was laid by 4 workers in 6 hrsso for 108 m of fencing need to be laid in 6 hrs by 4*6*108/(16*6)=27 workers