16 men can do apiece of work in 10days.how many men are needed to complete the work in 40 days? |
|
Answer» Men DAYS can do work = 16 × 10 = 160 . Men required to do work in 40 days is 40x then 40x=160 ; x=4 so 4 men are required |
|