15 men can finish the work in 40 days. the number of days in which the piece of work can be done by 20 men.Note: Do it step by step.. |
|
Answer» 15. 40 20. ?(X) number of men and time is in DIRECT proportion 15:20::40:x therefore time=20×40/15=54 days |
|