100 Men were employed to finish a work in 180 days. After 60 days it was found that only 1/5 of the work was done. How many more men must be employed to finish the work in the stipulated time ?1. 1802. 1603. 1004. 1505. 140 |
|||||||||||||||
Answer» Correct Answer - Option 3 : 100
|
||||||||||||||||