100 Men were employed to finish a work in 180 days. After 60 days it was found that only 1/5 of the work was done. How many more men must be employed to finish the work in the stipulated time ?1. 1802. 1603. 1004. 1505. 140

Answer» Correct Answer - Option 3 : 100
M1 × D1 = M2 × D2
W1W2
 
100 × 60 = a × 120
1
5
1 – 1
5


⇒ a = 200

⇒ Total workers  =  200 

⇒ Extra men required = 200 - 100 = 100