1. If 15 men can do a piece of work in 10 days, then how many menrequired to complete it in 50 days?(20(A) 2 (B) 3 (C) 4 (D) 5​

Answer»

\huge\sf\underline{\red{Answer}}

50 days / 10 days : 5

15 MEN / 5 = 3

The answer is: 3 men